DURATION
March 2019 - December 2019
OVERVIEW
The Glenbrook Station Upgrade is part of the NSW Government initiative to improve accessibility within the Transport Access Program. The program initiative is to provide a better experience for public transport customers by delivering accessible, modern, safe, and integrated transport infrastructure.
SCOPE OF WORK
-
Platform Works - Lift Base, Pit and Shaft Up to Foot Bridge Level
-
Platform slab Reinstatement – Possession works
-
Platform Regrading – Possession Works
-
Padmount Substation
-
New pedestrian Ramp on Buffit Parade
-
Strip footings, Retaining walls and Stairs
-
Precast Ramp works ( Cast on site)
All concrete quality has been completed as per RMS QA specification B80.