top of page
![](https://static.wixstatic.com/media/b01ae0_7fa2cd4b45ab42b687248362448fe508~mv2.jpg/v1/fill/w_720,h_480,al_c,lg_1,q_80,enc_avif,quality_auto/b01ae0_7fa2cd4b45ab42b687248362448fe508~mv2.jpg)
Hazelbrook Station
PROJECT
Hazelbrook Station Upgrade
CLIENT
Downer EDI Works
SECTOR
Transport/Rail
STATUS
Completed
DURATION
August 2019-December 2019
OVERVIEW
The Hazelbrook Station upgrade and commuter carpark is part of the NSW Government initiative to improve accessibility within the Transport Access Program (TAP) by delivering accessible, modern, safe, and integrated transport infrastructure.
Damcon was awarded the FRP concrete package and successfully worked near pedestrian traffic and live rail conditions without interrupting live rail and commuters.
SCOPE OF WORK
-
Foot Bridge – Topping Slab Works
-
Waterproofing
-
Night Works - Concrete Placement
All concrete quality as per RMS QA specification B80.
bottom of page